Plans continue to expand county water service to the Kittrell area, and county commissioners received a project update from Manager Jordan McMillen at its January meeting.
As things stand now, construction could begin as early as fall 2022 of the Phase 1B Water District, which includes laying about 25 miles of new water lines and making upgrades to the existing Kittrell water tower.
McMillen told WIZS News Thursday that the county water project is within $10,000 of breaking even – some unexpected repairs and additional costs have pushed that break-even point out a bit, but added “we are very satisfied with the progress we have made in bringing our system to self-sufficiency the past few years.”
The recently presented audit from fiscal year 2020-21 indicated that the water fund is within $10,000 of breaking even, which represents an improvement from being nearly $20,000 the previous year.
As for the Phase 1B work being done in the Kittrell area, McMillen said if all goes according to schedule, it could be complete by November 2023.
There have been some slight delays involving permitting issues, but once those are resolved, the bids could be advertised by April 2022, awarded in July and proceed with construction in September, McMillen said.
The total construction project would be scheduled for completion by August 2023.
Federal grant and loan projects awarded to Vance County for improving the drinking water for county residents is helping to make the upgrades and extensions to county residents.
McMillen said public meetings and signup efforts will ramp up once the county is closer to the construction phase.
Some of the roads east of Kittrell that will have new water lines installed include portions of Bobbitt Road, Peter Gill Road, Abbott Road, Dick Smith Road, South Chavis Road and Kittrell Road, he said.