Oxford Water/Sewer Improvements and Adjusting to get the Big Bucks to do It

Some residents of Oxford may be annoyed at the rat-a-tat of jackhammers as they chew up sidewalks or asphalt. Others may grimace when they see the ‘Road Work Ahead’ sign marking street construction. But these sights and sounds also are the marks of progress on the city’s infrastructure improvement plan.

In an effort to keep the public informed about what work is going on where, the City of Oxford has begun sending out monthly updates to outline where crews will be working.

Oxford Mayor Jackie Sergent said the idea arose from a town commissioner planning retreat. “It was a simple desire to be more effective at letting people know where work will be happening,” she said in an interview Monday. People want to know, Sergent said, where the work is being done and how long it’s going to take to complete.

The “where” is easy; it’s the “how long” that is less certain, she said.

The improvements are being made as part of a long-range comprehensive improvement plan to make upgrades to the water and sewer infrastructure. Grants and no-interest loans through the 2015 Connect NC bond legislation were available, but the city first had to adjust its water/sewer rates to qualify. Long story short, Sergent said, in the five years since, the city has gotten $50 million – $10 million in grants and more than $25 million in 0-interest loans.

This is a huge undertaking,” Sergent noted. “I am incredibly proud of what we’re doing,” but added that it certainly is not “glamorous.”

Visit www.oxfordnc.org/community/comprehensive_plans_projects.php to learn more. Call 919.603.1100 with questions or concerns.

NCSWIA awards Oxford $10 Million in Water and Sewer Infrastructure Funds

For Immediate Release

In February of 2016 City Engineer Amy Ratliff recommended that the City apply for NC Connect, North Carolina State funds. Faced with aging water and sewer infrastructure that in places dates back to 1907, the Commissioners approved the recommendation and ordered a plan to proceed.

 

In September of 2016, The Board of Commissioners approved a water and sewer rate increase to meet minimum rates required by the State of North Carolina to apply for the water and sewer grants and loans to allow Oxford to be in a better position to maintain both existing and new infrastructure well into the future.

 

City Engineer Ratliff led the team that developed a $96 million Ten Year Capital Improvement Plan (CIP) that was adopted by the Board in regular session on September 13th, 2016. Project planning on the improvements is already underway and construction is slated to start on the water and sewer infrastructure as early as this summer.

 

On January 18th 2017, the North Carolina State Water Infrastructure Authority, voted unanimously to grant the City of Oxford over $6 Million in state grants and nearly $4 Million in 0% interest loans to replace over nine miles of water and sewer infrastructure within the Oxford city limits.

 

Securing this funding is the first step in fortifying the water and sewer infrastructure in Oxford. Residents will notice work on these infrastructure improvements in the coming months. The completed system will pave the way for continued residential and commercial growth in our community.

 

Much of the water and sewer infrastructure upgrades need to be completed in time for the City to piggy-back on the North Carolina Department of Transportation resurfacing project scheduled to begin in the spring of 2018. By working with DOT, The City of Oxford will be able to resurface about four times as many road-miles as they have in the past.